Construction

Ready to build the Assembly Hall of the Tokamak

ITER Tokamak Assembly building – artistic impression (Courtesy:ENIA Architectes)

The ITER construction platform is getting ready for another major development! The consortium made of Vinci, Ferrovial and Razel will start the construction of the Tokamak Assembly Hall building in August 2014. The 60 metres high building, adjacent to the Tokamak complex, will host the two 750 tonnes cranes that will assemble the components of the ITER machine. The work is part of the construction contract for the Tokamak complex which was signed in 2012.

In April 2012, works kicked off with the drilling of boreholes and the extraction of 12000 m3 of soil and rock. Reinforcement works and the pouring of concrete for the 6000 m2 basemat followed which lasted roughly one year.

The construction of the impressive steel-structure will be realised in 15 steps from the erection of columns for the structure foundations to the assembly of the roofing in the ground floor.
Work will end in the first quarter of 2015.

The upper basemat of the Tokamak complex almost completed

Panoramic view of the Tokamak complex upper basemat, June 2014 – AIF Copyright

The construction of the 9300m2 upper basemat, so-called B2 slab, will come to an end in summer 2014. This slab will stand above the anti-seismic layer, put in place for the Tokamak complex composed of a 1.5 metres thick slab and 493 plinths, equipped with anti-seismic bearings.
The completion of this slab will mark a significant milestone. Once this is over, the construction of the ITER Tokamak complex can begin.
Currently, around 3000 tonnes of reinforcement have been installed, totalling 6 layers of rebars on average.

Since December last year, concrete pouring activities have started performed by GTM and Vinci Group. Four plots out of 15 have been poured already. A total of 15 000m3 of concrete will be used for the whole slab.

Watch our clip reporting on the key construction milestones

martial

Recent Posts

ITER Organization looks for a new Director-General

Lead the biggest international fusion project to date.

2 days ago

F4E announces the winners of the Supply Chain Excellence Awards

Companies recognised for an outstanding contribution to Europe’s fusion projects.

2 days ago

F4E presents Llevant, a breakthrough in nuclear analysis

The software can visualise complex geometric models in 3D within seconds.

6 days ago

How did F4E build the European fusion supply chain?

New report explains the industry’s evolution over nearly two decades.

1 week ago

Europe signs its first Procurement Arrangements for IFMIF-DONES

F4E commits to provide the accelerator’s injector and raw steel.

2 weeks ago

Swiss expertise to power up ITER

F4E and Ampegon hand over more power supplies and will provide two extra units.

2 weeks ago