The ITER Council, at its11th meeting (IC-11) in November 2012, requested the ITER Management Advisory Committee (MAC) to have a special meeting to assess the implementation of corrective actions proposed by ITER IO and Domestic Agencies focusing on critical and super-critical components/systems including the assembly plan. The MAC was asked to propose, if necessary, additional actions to realise the schedule approved as the 2010 Baseline.
The MAC held this 2nd special meeting in Barcelona on 18 and 19 March 2013. MAC Chair Ranjay Sharan, ITER IO Director-General, Professor Osamu Motojima, heads of the six Domestic Agencies, delegates representing all ITER Parties, and relevant IO representatives, gathered together to discuss issues related to maintaining the ITER project’s schedule, focusing on:
• Assessment of schedule development;
• Assessment of the list of critical items and super-critical items;
• Assessment of the implementation of corrective actions proposed by the Unique ITER Team (UIT);
• Encouragement of the UIT to adopt additional corrective actions to realise the schedule recovery and to assess a realistic First Plasma date.
F4E accelerates delivery in collaboration with Ansaldo Nucleare, Westinghouse and Walter Tosto.
F4E Director and staff members present progress in fusion projects and industrial benefits.
F4E, Daher and CFT barge operations receive ‘Green Shipper’ prize at an international forum.
Close to 6 billion EUR of added value and 5,600 jobs per year generated in…
Commissioning will lead to new plasma operations by the end of 2026.
Close to 900 sensor coils around the machine to track the plasma.