Manufacturing

Europe completes the production of its superconducting wire for the Toroidal Field coils

Final Inspection on the completed wire with an Eddy Current test station at Bruker EAS (courtesy of Bruker EAS GmbH)

F4E in collaboration with Bruker European Advanced Superconductors and Oxford Superconducting Technology, concluded an important milestone linked to Europe’s contribution to ITER’s powerful magnets. Due to their size and complex technical specifications, an outstanding production of Nb3Sn (Niobium-Tin) superconducting wire was recorded exceeding all the typical annual rates of production before ITER came to play.
The wire is the key component that will allow the TF coils to reach the impressive magnetic field of 12 T required for the plasma to be confined in the ITER machine. Its diameter is less than 1 mm and can sustain very high currents around 200 A when cooled down to low temperatures  at -269 degrees Celsius. Altogether 97 tonnes of the superconducting wire have been produced, tested, approved by F4E and cleared by ITER International Organization.
The amount of wire manufactured by the two companies includes more than 1,500 production units, used to fabricate the cables for the European TF coil cable-in conduit conductor lengths. The total wire length produced exceeds 20,000 km which is around half of the earth’s circumference.
This wire is already used in the manufacturing of the European TF conductors for which around 50% of the lengths have been already fabricated and delivered to ASG facilities in Italy where the works for the TF coil winding packs are being carried out. The production of the remaining European TF conductor lengths will be completed in 2015.

martial

Recent Posts

F4E delivers all equipment to distribute cooling power in ITER

The last cryolines are onsite and their installation will begin soon.

4 days ago

ITER Test Blanket Modules move forward

Europe advances its two concepts through Preliminary Design Review.

1 week ago

Europe develops a new fuel source for JT-60SA

A key technology mastered as F4E and Sener deliver centrifuge accelerator.

3 weeks ago

Europe gets ready to manufacture ITER’s upper launchers

F4E and partners finalise the design of a complex plasma heating component.

3 weeks ago

F4E Supply Chain Excellence Awards launched

Five categories to recognise outstanding industrial contributions in fusion.

4 weeks ago

F4E publishes the first Global Fusion Energy Trends report

What is the state of play in funding, research, patents and devices?

1 month ago