Europe installs its first tank at the ITER Cryoplant

Installing Europe’s first Gaseous Helium tank at the ITER Cryoplant, Cadarache, February 2018 © ITER IO

On Wednesday 14 February, the heartbeat of the impressive ITER Cryogenic facility started to beat faster welcoming on its premises the first of the six gaseous helium (GHe) tanks that Europe has been responsible to manufacture.

A lifting operation which started early in the morning was successfully concluded when the component, measuring 25 m and weighing 150 t, was placed on a 2.5 m foundation made of concrete and steel. As the workforces were tightening the bolts, and the tank was firmly fixed on the ground, there was a moment of rejoice from all the workforces involved in this task. The hard work of the previous years, from designing this tank to finally transporting it on-site, had paid off. The tank took its final position on the site of the biggest fusion experiment.

“This delicate operation required a lot of planning to ensure the lifting of 150 t safely and in a timely manner. It took roughly one week to assemble the different parts of the crane we had to use. Every movement had to be carried out with extreme precision given the load it was lifting” explained Marc Simon, F4E’s Deputy Head of Cryogenics overviewing this technical achievement.

Representatives of F4E, ITER IO, Air Liquide, Technilevage, Altead and IREM standing in front of the Gaseous Helium (GHe) tank that has just been installed, ITER Cryoplant, Cada

The installation of the tank has been the result of the excellent team work between F4E and the ITER Organization, together with a number of F4E industrial partners such as Air Liquide, responsible for the fabrication and installation of the tank; the VFR consortium (Vinci Ferrovial and Razel-Bec) managing the construction of the Tokamak complex and the auxiliary buildings; Technilevage, Altead and IREM- Air Liquide subcontractors- performing this operation.

The GHe tanks will recover the helium from the ITER machine and provide a buffer during its operation. Each of them will store roughly 800 kg of helium. As part of ITER’s cryogenic system they will play an important part in the operations required to cool down the machine to -269˚ C and store the gases.

In the months to follow, 15 more large lifting operations are planned to be performed at the ITER Cryoplant facility together with the installation of more equipment by Air Liquide, INOX, M+H on behalf of the Omega consortium, Demont, Linde and AS Scientific.

Representatives of F4E, ITER IO, Air Liquide, Technilevage, Altead and IREM standing in front of the Gaseous Helium (GHe) tank that has just been installed, ITER Cryoplant, Cadarache, February 2018 © ITER IO
martial

Recent Posts

The first Inner Vertical Target is ready for ITER

F4E and Research Instruments advance in series production.

2 days ago

Europe’s final ITER Vacuum Vessel sector delivered

The arrival of ITER’s last extra-large component closes a 16-year manufacturing journey by F4E and…

4 days ago

F4E launches the 2026 Fusion Technology Transfer Award

10,000 EUR for projects that take fusion solutions to the market.

1 week ago

F4E and Amazemet sign a collaboration agreement

A framework for cooperation in additive manufacturing and advanced materials.

1 week ago

F4E helps experts to map critical fusion technologies

Six reports are now available to guide R&D in Europe.

2 weeks ago

A step up in fusion: Europe and Japan train the next generation at JT-60SA

Students and early-career researchers learn from experts at the world’s largest tokamak.

3 weeks ago