Manufacturing

F4E radial plate suppliers start production

2 pre-machined radial plates ready for electron beam welding operations in the welding shop (copyright Christophe Chabert)

CNIM Industrial Systems and SIMIC Spa have started manufacturing the first of the 70 radial plates that will support the superconducting cables of ITER’s Toroidal Field coils. The components will essentially confine the hot plasma with the help of powerful magnets. Each company will have to manufacture 35 radial plates that measure 14m by 9m. We visited the facilities of the two companies to find out how works are advancing.

CNIM’s building at its Brégaillon industrial site has been renovated, and a brand new 3000m² production hall has been constructed close to the sea, to facilitate the transportation of large items that will be manufactured. The new building is fully air-conditioned to enable equipment to be kept at a constant temperature during its final machining. Inside the building, a 36m by 9m portal machining centre stands out “ready to machine two radial plates simultaneously to a precision of several tens of microns”, as Jean-Claude Cercassi, CNIM Commercial Development Manager, confirms. Work is progressing fast at CNIM after the first batches of raw materials were delivered. “The stainless steel segments have been machined and we are about to start with the electron beam welding,” Cercassi explains. This is now possible thanks to the installation of a dismountable vacuum chamber.

SIMIC Spa has also built a new industrial building in Porto Marghera to accommodate the production of the radial plate prototype, with brand new facilities and tooling, in order to support the production of the radial plates. A massive portal machine has been installed, which will operate in addition to the existing one that was used for the machining of the prototype, to manufacture the 35 radial plates. Marianna Ginola, SIMIC Spa, explains that “the manufacturing phase of the radial plates is the most exciting part of our contribution to the project. Our new building is ready, new tooling is in place. The production of the radial plates has started! This is a turning point for the project because the design starts taking shape and the impressive milling machine that SIMIC has invested into is put to operation. Our expertise will be fully deployed to deliver these key components”.

The first radial plates are scheduled to be completed in July, when they will be transported by sea to La Spezia (Italy) to be fitted inside the ITER Toroidal Field coils at a facility run by ASG Superconductors. After producing a second radial plate five weeks later, CNIM and SIMIC Spa are expected to accelerate production to a rate of one plate every four weeks.

To learn more about the manufacturing of TF coil components click here.

Gantry machine to be used for the radial plates final machining operations (SIMIC copyright)


Gantry machine to be used for the final machining operations on 2 radial plates at the same time (copyright CNIM/Christophe Chabert)


martial

Recent Posts

The first Inner Vertical Target is ready for ITER

F4E and Research Instruments advance in series production.

1 week ago

Europe’s final ITER Vacuum Vessel sector delivered

The arrival of ITER’s last extra-large component closes a 16-year manufacturing journey by F4E and…

2 weeks ago

F4E launches the 2026 Fusion Technology Transfer Award

10,000 EUR for projects that take fusion solutions to the market.

2 weeks ago

F4E and Amazemet sign a collaboration agreement

A framework for cooperation in additive manufacturing and advanced materials.

2 weeks ago

F4E helps experts to map critical fusion technologies

Six reports are now available to guide R&D in Europe.

3 weeks ago

A step up in fusion: Europe and Japan train the next generation at JT-60SA

Students and early-career researchers learn from experts at the world’s largest tokamak.

4 weeks ago