F4E signs the Procurement Arrangement on Divertor Cassette Integration

3D view of the ITER Divertor Cassette Body and PFCs


F4E and ITER IO have concluded the Procurement Arrangement (PA) for the Divertor Cassette Body and Integration. The PA, signed in May and worth 11.2 kIUA of ITER credits, concerns the manufacturing of 60 Cassette Bodies, the mounting of the three Plasma-facing Components (PFCs) on them, and the installation of Diagnostics and instrumentation on a certain number of them. The signing of the PA is an important step in the procurement of the Divertor, a crucial component of the ITER machine.

The implementation of the PA will follow four main phases: firstly, the fabrication and qualification of a Cassette Body prototype and the integration of Plasma-facing Component prototypes on it; secondly, the series production of the Cassette Bodies, factory acceptance tests and delivery to the integration site; thirdly, the assembly of the Plasma-facing Components and Diagnostics (where applicable) on the Divertor Cassette Bodies, thus producing a Cassette Assembly; and lastly final acceptance testing of the Cassette Assemblies and their delivery to the ITER site.

Located at the very bottom of the Vacuum Vessel, the ITER Divertor is made up of 54 remotely-removable Cassette Bodies, each holding three Plasma-facing Components (namely, the inner and outer vertical targets and the dome – see figures 1 & 2). The Cassette Body, to be made of stainless steel 316 L(N) ITER grade, will have a total mass of  4.7 tonnes (7.9 tonnes if the PFCs are mounted on it). The technical design will enable the targets, in their lower part, to intercept the magnetic field lines, and therefore remove the high heat load coming from the plasma. The upper-curved part of the targets will provide a baffle which will limit the neutral particle flow, and prevent it from extinguishing the fusion reaction. The dome will also baffle neutral particles and protect the Cassette Body from direct contact with the plasma. The Divertor Cassette Assemblies will be fixed to the Vacuum Vessel using attachments made out of aluminium bronze.

F4E foresees that the PA will generate two contract lines: one for the fabrication of Cassette Bodies for which a Call for Tender will be launched before the end of 2012; and another one for PFCs and Diagnostics/instrumentation integration and the final acceptance tests, for which a Call for Tender will be launched during the course of 2014.

Location of the ITER divertor in Vacuum Vessel.

martial

Recent Posts

F4E contract signed to deliver ITER assembly tools

Five suppliers will compete to support divertor, neutral beam and port plug handling systems.

2 days ago

Europe delivers all cold valve boxes for the ITER neutral beam cryopumps

F4E and Research Instruments complete the contract on schedule.

6 days ago

Investment in fusion private sector initiatives reaches 13 billion EUR

F4E Fusion Observatory report analyses competing models in US, China and Europe.

1 week ago

Multilateral International DONES Agreement signed

F4E, Spain, Japan, Croatia and Italy will cooperate to build IFMIF-DONES.

2 weeks ago

Europe and Japan install a powerful section in LIPAc

The connection to the accelerator will pave the way for groundbreaking operations.

4 weeks ago

F4E and SAES Rial Vacuum deliver JT-60SA diamond windows

The components will let microwaves into the machine whilst keeping it sealed.

1 month ago