Construction

Flashback of the ITER construction

ITER construction site June 2011


To make sense of what has been achieved so far, we have decided to look back on some key moments of the ITER construction site in order to grasp the volume of progress. We are amazed to see how quickly the site has changed over the last six months with works ongoing at the Poloidal Field (PF) coils building and the Tokamak complex.

The PF coils building measures approximately 250 metres long, 45 metres wide and 17 metres high.

It will include regular building services (HVAC, electrical, piping), two large cranes (one standard crane weighing 25 tonnes, and one special crane weighing 50 tonnes), a small set of offices, a parking and two docking areas for the unloading and temporary placement of coils.

The works started in autumn last year when the first walls were erected. It was in early January though that the PF coils building became increasingly visible. In February, the steel beams were put in place serving as the structural element support to bear the load of all roofing and March found the F4E contractors dealing with the inner layer of the walls and cladding. Between April and May, the full volume of the building, where the biggest PF coils will be assembled, stood out on the ITER platform and works on antirust cladding took off together with metal sheeting and Rockwool insulation. In June, the 25 tonnes crane was installed and the cooling towers arrived on the roof top of the building.

The excavation for the Tokamak complex started in autumn last year going 20 metres deep and excavating around 200,000 m3 of rock, approximately the same volume as 43 of London’s Big Ben tower. The construction of the reinforced concrete basemat and walls forming the seismic isolation pit structure involves the casting of approximately 35,000 m3 of reinforced concrete. By February this year, the Tokamak pit got a flat surface on which the construction of the base slab on which the construction of the Tokamak, Tritium and Diagnostics buildings would begin.  By March, the Tokamak excavation was completed and a steel safety mesh was installed on the rock slopes to create a safe working environment for additional soil investigation and rock joint treatment. In June, the first layer of the blinding concrete was poured and the works of steel reinforcement began.

Discover step-by-step the progress on the ITER construction site by visiting the 2010 -2011 image galleries and our multimedia section.

PF coils field building (June 2011)


PF coils field building (January 2011)


Tokamak complex (June 2011)


Tokamak complex (February 2011)

martial

Recent Posts

Europe starts works for new ITER heating buildings

F4E and partners will construct three additional facilities and two bridges.

5 hours ago

ITER Organization looks for a new Director-General

Lead the biggest international fusion project to date.

3 days ago

F4E announces the winners of the Supply Chain Excellence Awards

Companies recognised for an outstanding contribution to Europe’s fusion projects.

3 days ago

F4E presents Llevant, a breakthrough in nuclear analysis

The software can visualise complex geometric models in 3D within seconds.

1 week ago

How did F4E build the European fusion supply chain?

New report explains the industry’s evolution over nearly two decades.

1 week ago

Europe signs its first Procurement Arrangements for IFMIF-DONES

F4E commits to provide the accelerator’s injector and raw steel.

2 weeks ago