The clip shows that the six year assembly of JT-60SA is moving forward: the heart of the machine, the vacuum vessel, is now being built.


See the progress of the JT-60SA project – one of the three projects being developed under the Broader Approach Agreement – in this new clip filmed on-site in Naka, Japan. The clip shows that the six year assembly of JT-60SA is moving forward: the heart of the machine, the vacuum vessel, is now being built.

Implemented by the Japan Atomic Energy Agency (JAEA) and F4E, the advanced superconducting JT-60SA tokamak (SA stands for super advanced) will be used to quickly identify how to optimise plasma performance for ITER and will study advanced modes of plasma operation suitable for DEMO. A first plasma is foreseen for March 2019.

The JT-60SA vacuum vessel consists of 10 sectors made of 316 L stainless steel, 6.6 m high and 3.5 m wide, each weighing around 17 tonnes. The clip shows the placing of the first two sectors which will now be welded together. It is foreseen that the remaining sectors will be added to the structure at the rate of one per month, although before the placing and welding of the last sector, the 18 Toloidal Field coils (magnets which will keep the plasma in place during the fusion process) produced in Europe will be threaded over the vessel and fixed in place.

To learn more about the Broader Approach agreement and its projects, visit the Broader Approach website or download the Broader Approach brochure.

(Film clip courtesy of Ibaraki News)

martial

Recent Posts

F4E delivers all magnetics diagnostic equipment for ITER

Close to 900 sensor coils around the machine to track the plasma.

2 days ago

Metromecánica wins Fusion Technology Transfer Award

The company adapted a robotic metrology tool from ITER to the automotive industry.

1 week ago

Europe’s third ITER Vacuum Vessel sector completed

Teamwork by F4E and AMW consortium to deliver on schedule.

2 weeks ago

Europe hands over the first power supply unit to heat ITER

A major step in commissioning by F4E and Ampegon.

2 weeks ago

F4E and Gauss Fusion sign collaboration agreement

A framework for knowledge exchange in areas like magnets or tritium breeding.

4 weeks ago

The Cask Transport System, an automated vehicle ready for ITER assembly

F4E, Solving and Ansaldo Nucleare simulate lifting and moving port plugs in Finland.

1 month ago