JT-60SA Toroidal Field Magnet PA signed

JT-60SA TF coil, structure, and cross section


In July, the Japanese Atomic Energy Agency (JAEA) and F4E signed the Procurement Arrangement (PA) for the Toroidal Field (TF) magnet for the JT-60SA project, one of the three projects covered by the Broader Approach Agreement between Europe and Japan.

Representing approximately 40% of Europe’s hardware contribution to the project, the PA opens the way for the procurement of a component key to holding the tokamak plasma in place. It foresees the manufacture of the NbTi coil conductor and power supply feeder connections, 18 TF coils, each consisting of a conductor winding pack and steel case, intercoil structures to resist the overturning forces on the TF coils due to the nearby strong poloidal field, and 18 gravity supports to take the combined weight of the above. It defines the requirements and interfaces for design, fabrication, works tests, and transport to the port of entry in Japan, and for works acceptance of the TF coils by the JT-60SA project.

The work will be carried out, for their respective parts, by contractors chosen by F4E, as well as by the Voluntary Contributors CEA (French Atomic Energy and Alternative Energies Commission) and ENEA (Italian National Agency for New Technologies, Energy and Sustainable Economic Development).

Delivery of the first TF coil is foreseen in October 2013.

martial

Recent Posts

F4E Supply Chain Days bring together European companies of different sizes

A forum to strengthen ties and shape fusion procurement and contracts.

4 days ago

Axon’ Cable wins F4E Technology Transfer Demonstrator Call

50.000 EUR for adapting an ITER cable solution to space or particle accelerators.

2 weeks ago

New diagnostic systems in progress to upgrade JT-60SA

Europe and Japan collaborate to monitor next plasma operations.

2 weeks ago

F4E Roundtable Key Takeaways report now available!

A summary of the ideas and actions proposed by EU fusion stakeholders.

3 weeks ago

Europe completes the Control Building, the operations centre of ITER

Servers and workstations are installed as the first teams move in.

3 weeks ago

F4E and CERN join forces in fusion energy and particle physics

The two leading organisations ready to break new ground in Big Science.

4 weeks ago