Major equipment of ITER cryoplant is ready

The liquid helium inner-tank, designed and manufactured by CryoAB, part of the contract signed between Air Liquide Global and EC Solutions and Fusion for Energy, February 2016.

It’s hard to miss the inner tank of ITER’s liquid helium tank even in the spacious facility where it has undergone a leak detection test. This massive piece of equipment, whose volume is 190 m3 and measures 23 m in length by 3.5 m in diameter, will store part of ITER’s liquid helium and will be assembled subsequently inside a bigger tank. The impressive size of components is one of the underlying themes of the ITER project and as you may have guessed its cryoplant will be the biggest-ever.

Manufacturing of the inner-tank started in November 2015 and was completed earlier this year. This piece of equipment stems from a lengthy process of preliminary and final design reviews where F4E, Air Liquide Global E&C SolutionsITER International OrganizationITER India, together with independent experts, critically assessed specifications before production started. The inner-tank, designed and manufactured by CryoAB, is made of stainless steel and has multi-layer insulation to minimise any thermal losses so that the temperature inside remains at 4 K/-269 ˚C. Externally it will be covered by another component, known as a thermal shield, which will be made of aluminum and its function will be to minimise any thermal losses as well. When the tank is filled with liquid helium, its weight will reach 88 tonnes, the equivalent of 58 mid-sized cars. Now here comes a twist: after the one tank goes inside the other and the entire structure is fully assembled it will be positioned 7.6 metres high. The entire system has been designed in such way so as to cope with the potential of a seismic event.

To complete the manufacturing process of the inner-tank, it had to undergo a leak detection test. It took almost half a day for technicians and engineers to inspect 500 m of linear welds performed to join the different sectors of the tank. Representatives from F4E together with teams of Air Liquide Global E&C Solutions, witnessed the exercise managed by CryoAB and acknowledged that it was successfully completed. The equipment will arrive to the ITER site towards the end of the year.

CryoAB technicians carrying out the liquid helium leak test on the inner-tank. It took almost half a day to inspect roughly 500 m of linear welds. February 2016.


martial

Recent Posts

F4E welcomes European Commissioner for Energy and Housing Dan Jørgensen

Fusion will contribute to Europe’s energy security and competitiveness.

3 days ago

F4E launches the 2026 Technology Transfer Demonstrator Call

Two selected projects will get up to 50.000 EUR to apply fusion know-how in the…

3 days ago

Europe’s fourth Vacuum Vessel sector is ready for ITER

F4E accelerates delivery in collaboration with Ansaldo Nucleare, Westinghouse and Walter Tosto.

1 week ago

Vice-President of the European Commission Teresa Ribera visits F4E in Barcelona

F4E Director and staff members present progress in fusion projects and industrial benefits.

2 weeks ago

An award for Europe’s heavy transport and logistics for ITER

F4E, Daher and CFT barge operations receive ‘Green Shipper’ prize at an international forum.

3 weeks ago

Europe’s economy benefits from F4E activities according to new study

Close to 6 billion EUR of added value and 5,600 jobs per year generated in…

1 month ago