Construction

More progress on the ITER construction site

View of the mock-up that was created to test construction techniques.

A 150 m2 mock-up has been completed on the ITER platform in parallel with the on-going propping and formworks activities of the second concrete slab, otherwise known as B2 slab in the ITER construction jargon. This upper base slab, which is 1.5 meters thick, will be supported by the 493 anti-seismic bearings and plinths.
Nicolas Vendeuvre, working for ENGAGE, the consortium managing the Architect Engineer contract for the ITER buildings, explains that ‘’this mock-up was initiated to test the methodology of the GTM Sud, member of the Vinci construction group, in order to draw lessons on our own design before carrying out the construction”.
The mock-up reflects the four most complex areas of the B2 slab in terms of reinforcement:

First of all, the complex and dense reinforcement, especially at the boundaries between ‘radial’ and ‘orthogonal’, requires an arrangement of re-bars to mirror the round shape of the future Tokamak machine.
Second, all interface aspects between the re-bars and the embedded plates need to be taken into consideration. The embedded plates are the interface between the civil works and the process supporting system. Almost 1,600 embedded plates are expected to be installed for the whole slab.

Nicolas Vendeuvre explains that mock-ups are commonly used in such complex projects in order to have a better view on what is going to be built. “It is like a training area that helps us to make a final choice before launching the actual construction. Basically, this kind of exercise helps the contractor to identify ways of improving the process and work procedures”, he adds.
Today, the mock-up is ready for new tests aiming to demonstrate that concrete will be well poured without undesirable pockets within such a dense reinforcement.

Almost 1,600 embedded parts to be installed.


martial

Recent Posts

F4E Supply Chain Days bring together European companies of different sizes

A forum to strengthen ties and shape fusion procurement and contracts.

3 days ago

Axon’ Cable wins F4E Technology Transfer Demonstrator Call

50.000 EUR for adapting an ITER cable solution to space or particle accelerators.

1 week ago

New diagnostic systems in progress to upgrade JT-60SA

Europe and Japan collaborate to monitor next plasma operations.

2 weeks ago

F4E Roundtable Key Takeaways report now available!

A summary of the ideas and actions proposed by EU fusion stakeholders.

2 weeks ago

Europe completes the Control Building, the operations centre of ITER

Servers and workstations are installed as the first teams move in.

3 weeks ago

F4E and CERN join forces in fusion energy and particle physics

The two leading organisations ready to break new ground in Big Science.

4 weeks ago