Construction

Read about the latest progress on the ITER site and watch our new clip

Progress of the work at the Contractors’ area on the ITER site, November 2012

On the ITER platform, work is progressing well on the Assembly Hall of the Tokamak complex area. This 57 metre high building of 5400 m² is located next to the Tokamak pit, and will host the two main cranes of 750 tonnes that will support the assembly of the components of the ITER machine. In November, the pouring of the blinding concrete was concluded and the reinforcement activities that will end up using approximately 1,400 tonnes of steel carried on. The first plot of structural concrete was poured in mid-November and the next plot will be poured in the next days.
Progress has also been made around the Tokamak complex area where excavation works for pipes, water drainage and galleries have started. As far as the contractors’ area is concerned, the foundations of the canteen building are completed and 70 modular buildings are installed.

martial

Recent Posts

F4E contract signed to deliver ITER assembly tools

Five suppliers will compete to support divertor, neutral beam and port plug handling systems.

2 days ago

Europe delivers all cold valve boxes for the ITER neutral beam cryopumps

F4E and Research Instruments complete the contract on schedule.

6 days ago

Investment in fusion private sector initiatives reaches 13 billion EUR

F4E Fusion Observatory report analyses competing models in US, China and Europe.

7 days ago

Multilateral International DONES Agreement signed

F4E, Spain, Japan, Croatia and Italy will cooperate to build IFMIF-DONES.

2 weeks ago

Europe and Japan install a powerful section in LIPAc

The connection to the accelerator will pave the way for groundbreaking operations.

4 weeks ago

F4E and SAES Rial Vacuum deliver JT-60SA diamond windows

The components will let microwaves into the machine whilst keeping it sealed.

1 month ago