See the progress of the ITER construction site

80% of the propping & shoring towers installed – May 2013

During the months of April and May we have been busy taking pictures of the ITER construction site so that you see its progress.
The reinforcement activities of the second concrete slab on the Tokamak pit have advanced and 80% of the propping and shoring towers have been installed.
The canteen is ready to receive its equipment. There has been good progress on the critical areas network and the galleries around the Tokamak complex.

To view and download the latest images from the ITER site visit our image gallery and our brand new F4E Flickr account which already boasts a nice selection of images and aerial views.

ITER site – Aerial View – June 2013 © M. Postollec, O. Gillain – Engage


martial

Recent Posts

F4E contract signed to deliver ITER assembly tools

Five suppliers will compete to support divertor, neutral beam and port plug handling systems.

2 days ago

Europe delivers all cold valve boxes for the ITER neutral beam cryopumps

F4E and Research Instruments complete the contract on schedule.

6 days ago

Investment in fusion private sector initiatives reaches 13 billion EUR

F4E Fusion Observatory report analyses competing models in US, China and Europe.

1 week ago

Multilateral International DONES Agreement signed

F4E, Spain, Japan, Croatia and Italy will cooperate to build IFMIF-DONES.

2 weeks ago

Europe and Japan install a powerful section in LIPAc

The connection to the accelerator will pave the way for groundbreaking operations.

4 weeks ago

F4E and SAES Rial Vacuum deliver JT-60SA diamond windows

The components will let microwaves into the machine whilst keeping it sealed.

1 month ago