See the progress of the ITER construction site

80% of the propping & shoring towers installed – May 2013

During the months of April and May we have been busy taking pictures of the ITER construction site so that you see its progress.
The reinforcement activities of the second concrete slab on the Tokamak pit have advanced and 80% of the propping and shoring towers have been installed.
The canteen is ready to receive its equipment. There has been good progress on the critical areas network and the galleries around the Tokamak complex.

To view and download the latest images from the ITER site visit our image gallery and our brand new F4E Flickr account which already boasts a nice selection of images and aerial views.

ITER site – Aerial View – June 2013 © M. Postollec, O. Gillain – Engage


martial

Recent Posts

Kilometres of pipes manufactured to cool down the core of ITER

Europe’s suppliers will use the tubes by DMV to shape the blanket manifolds.

4 days ago

Is Europe ready to lead the fusion energy race?

F4E Roundtable brings together policy makers, industry, SMEs, start-ups, and laboratories to shape tomorrow’s strategy.

2 weeks ago

European systems ready to power Japanese gyrotrons in JT-60SA

Integrated tests by F4E, QST, JEMA Energy achieved 1 MW of radio frequency power.

3 weeks ago

The F4E Fusion Observatory presents a report on private sector investment

Europe behind US in start-up market but leads in funding for the ITER supply chain.

3 weeks ago

The ITER Fast Discharge building is completed

F4E and European constructors also hand over the busbar bridges.

4 weeks ago

The foundations of IFMIF-DONES facility are laid

Japan joins the partnership as multilateral agreement progresses.

1 month ago