Construction

See the progress of the ITER construction site

80% of the propping & shoring towers installed – May 2013

During the months of April and May we have been busy taking pictures of the ITER construction site so that you see its progress.
The reinforcement activities of the second concrete slab on the Tokamak pit have advanced and 80% of the propping and shoring towers have been installed.
The canteen is ready to receive its equipment. There has been good progress on the critical areas network and the galleries around the Tokamak complex.

To view and download the latest images from the ITER site visit our image gallery and our brand new F4E Flickr account which already boasts a nice selection of images and aerial views.

ITER site – Aerial View – June 2013 © M. Postollec, O. Gillain – Engage


martial

Recent Posts

Europe and Japan celebrate completion of ITER Toroidal Field coils

Ministers, industry, scientists, and engineers pay tribute to the teams behind this remarkable achievement.

1 week ago

European steel for Test Blanket Modules arrives in Korea

F4E delivers 5.8 tonnes of EUROFER97

2 weeks ago

EU Fusion Business Forum unveils new market opportunities

Policy-makers, companies, start-ups and laboratories network and explore partnerships

2 weeks ago

Fusion energy – an EU flagship investment for green transition

F4E Director highlights prospect for innovation and growth in a conference.

1 month ago

Europe and Japan invest in supercomputers to boost fusion research

IFERC collaboration kicks off a new round of simulation projects.

1 month ago

Europe’s first cryopump delivered to ITER

F4E is collaborating with the RI-Alsymex consortium to manufacture eight of them.

1 month ago