Construction

The latest progress from the ITER site

Panoramic view of Assembly Hall area of the Tokamak complex, October 2012

On the ITER platform, work is progressing well on the Assembly Hall of the Tokamak complex area.
This 57 metre high building, located next to the Tokamak pit, will host the two 750 tonnes cranes that will assemble the components of the ITER machine.

On 20 September 2012, the first structural concrete was poured in one of the three galleries by GTM (VINCI Group contractor). It was considered a big step forward linked to the foundations works.
It all started back in April 2012, where 500 boreholes (soil investigations to detect any void in the rock) preceded the impressive phase of excavation. Scrapers and shovels dug to 2.5 metres deep to extract close to 12,000 m3 of soil. During summer, the blinding concrete pouring activities kicked off in order to flat level the surface and make way for the reinforcement activities that will end up using 1,400 tonnes of steel! The foundations works are expected to end by March next year.

The basemat design, measuring 2.2 metres thick in the perimeter and 1.2 metres thick in the centre, integrates openings for electrical galleries, drainage, piping and tunnels that will be connected to the Tokamak complex building. According to Miguel Curtido, F4E’s Technical Project Officer, “it will be the first time that we will have to coordinate the work of two contractors working in parallel and very close proximity in order to be comply with our planning”. In fact, other tunnels and precipitation drainage activities will be performed in parallel with works on the Assembly Hall foundations. ‘’Good coordination will be one of the daily challenges for the next years due to the complexity of the project and our commitment to deliver on time‘’ he added.

To view the latest pictures from the ITER construction site visit our image library.

martial

Recent Posts

The F4E Fusion Observatory presents a report on private sector investment

Europe behind US in start-up market but leads in funding for the ITER supply chain.

53 minutes ago

The ITER Fast Discharge building is completed

F4E and European constructors also hand over the busbar bridges.

7 days ago

The foundations of IFMIF-DONES facility are laid

Japan joins the partnership as multilateral agreement progresses.

2 weeks ago

F4E and Air Liquide get ITER’s Cryoplant ready

Commissioning of European systems advancing after successful mechanical tests.

3 weeks ago

F4E industrial partners give feedback on Fusion Expert Group report

Importance of ITER, private sector involvement and a stronger F4E amongst the key findings.

3 weeks ago

F4E and VTT advance remote handling solutions for ITER

New grant for the Finnish research centre to develop divertor assembly technologies.

1 month ago