Components

The manufacturing of the ITER Poloidal Field coils has started

CNIM technicians supervising the manufacturing of the European Poloidal Field coils in F4E’s Facility, Cadarache

The team of engineers from F4E, ASG and CNIM, working in Europe’s industrial facility on the ITER site, and their colleagues in ASIPP, the Institute of Plasma Physics of China’s Academy of Sciences, have officially started manufacturing the Poloidal Field (PF) coils assigned to Europe for the biggest fusion device –ITER. ITER will operate with six PF coils. Europe is responsible for five of them and through a collaboration agreement with China one will be fabricated in ASIIP. The remaining coil will be delivered by Russia.

After having successfully completed the winding tests using lengths of dummy conductor, the technicians have started unspooling the “real” conductor and inserted it in the machines to produce the impressive magnetic rings that will control the shape and stability of the super-hot plasma.

In ASIPP, the winding of the first Double Pancake (DP), which consists of two layers of conductors wound in the shape of massive pancakes, started in mid-March and has been completed. Works on the two Helium inlets at the inner joggles, from where Helium will circulate in the conductor to lower its temperature to freezing levels so as to make the coil superconductive, have been concluded. Carefully milling a hole in the jacket, without damaging the superconducting strand underneath, and welding a pipe to feed the helium into the conductor, have been some of the additional delicate works that needed to be performed. This weld has then been X-Rayed and leak tested to ensure that no Helium can escape through the weld. Subsequently, the Helium inlet insulation has then been wrapped around the inlet. On average, the winding of a DP is expected to take 4-5 weeks each.

The Winding of the first Double Pancake of Poloidal Field coil 6 has been completed, ASIPP, China

After a series of rigorous dimensional checks, in order to check whether the shape and dimensions of the component are in compliance, the component will be transferred to the terminal assembly area. The DP will enter its final stage of fabrication by going through Vacuum Pressure Impregnation, where the necessary vacuum will be created to inject the epoxy resin and cure the insulation.

Meanwhile, a few weeks ago in F4E’s PF coils facility, CNIM has already started winding the conductor of the fifth PF coil and the first DP is expected to be completed by the end of May. When the first layers will be completed, the team of technicians will proceed with the installation of the Helium inlets and perform the same steps as in ASIPP.

The first lengths of conductor unspooled for the manufacturing of the Poloidal Field coils in F4E’s facility, Cadarache

The good collaboration between F4E, ASIPP and their industrial partners, has been fundamentally important in making good progress in a co-ordinated way. The engineers and technicians supervising the works are witnessing the moment they have all been waiting for: the winding tests are over and the coils are being manufactured for real!

martial

Recent Posts

F4E welcomes European Commissioner for Energy and Housing Dan Jørgensen

Fusion will contribute to Europe’s energy security and competitiveness.

4 days ago

F4E launches the 2026 Technology Transfer Demonstrator Call

Two selected projects will get up to 50.000 EUR to apply fusion know-how in the…

4 days ago

Europe’s fourth Vacuum Vessel sector is ready for ITER

F4E accelerates delivery in collaboration with Ansaldo Nucleare, Westinghouse and Walter Tosto.

1 week ago

Vice-President of the European Commission Teresa Ribera visits F4E in Barcelona

F4E Director and staff members present progress in fusion projects and industrial benefits.

2 weeks ago

An award for Europe’s heavy transport and logistics for ITER

F4E, Daher and CFT barge operations receive ‘Green Shipper’ prize at an international forum.

3 weeks ago

Europe’s economy benefits from F4E activities according to new study

Close to 6 billion EUR of added value and 5,600 jobs per year generated in…

1 month ago