Transmission line connection to SPIDER vessel completed

Part of the 35 metre long transmission line which is connected to the SPIDER vessel

Under the stars and a bright shining moon, colleagues from F4E, COELME and Consorzio RFX celebrated: at eleven o’clock that night, the installation of the transmission line for SPIDER was completed at the Neutral Beam Testing Facility (NBTF) site in Padua, Italy. F4E have collaborated with the Italian company COELME in order to design, manufacture and install the 35 metre long transmission line which will connect the power supplies to the SPIDER beam source and transmit the energy required for its operation. The transmission line itself is not straight but deliberately built in a winding manner within a concrete labyrinth to ensure the containment of the particles generated in the SPIDER vessel. In addition, it is made up of double-layered panels of copper and calcium silicate in order to mitigate electromagnetic interferences coming from SPIDER’s ion source which could compromise the operation of the power supplies.

“Installation has involved a great deal of work on-site”, says Daniel Gutierrez, F4E Technical Officer responsible for the transmission line. “With such a long component, there are many things that could have gone wrong and installation is very much dependent on the layout, indeed very little pre-assembly can be done in the factory”, he explains.

Why was the installation completed only so late in the night? “In order to test that the transmission line is working properly, we need to ensure vacuum conditions in the SPIDER vessel”, explains Gutierrez “It took several days to achieve the right conditions, and by the time the conditions were right, it was already seven o’clock in the evening. If we would have stopped then, we would have had to start over, so we decided to continue – right up until eleven o’clock in the night”, he smiles.

The transmission line feeds power into the SPIDER (Source for Production of Ion of Deuterium Extracted from Radio frequency plasma) machine – a test bed where the first full-scale ITER ion source will be tested and developed. The ion source produces ions (particles with electric charges – either positive or negative), from which neutral particles originate. These neutral particles will be injected in the ITER plasma in order for the plasma to obtain the temperature and conditions necessary for the fusion reaction to occur. SPIDER is located in the Neutral Beam Test Facility – the facility which will test all main aspects of ITER’s neutral beam heating system.

martial

Recent Posts

F4E helps experts to map critical fusion technologies

Six reports are now available to guide R&D in Europe.

3 days ago

A step up in fusion: Europe and Japan train the next generation at JT-60SA

Students and early-career researchers learn from experts at the world’s largest tokamak.

5 days ago

Europe completes the last ITER Vacuum Vessel sector

F4E and AMW consortium manufacture their fifth sector ahead of schedule.

1 week ago

LIPAc gets ready to operate

Europe and Japan advance through commissioning and provide experience for DONES.

2 weeks ago

European Commissioner for Energy and Housing Dan Jørgensen visits ITER

The high-level EU politician calls for Europe to lead the way to commercial fusion.

3 weeks ago

ITER’s Vacuum Vessel comes together: the journey from factory to tokamak pit

A look at Europe’s five sectors advancing through manufacturing and assembly.

1 month ago