Our October clip offering an overview of the works carried out on the ITER construction site has just been released. We report on the progress of the site adaptation works and the Assembly Hall of the Tokamak complex area.
The excavation works for the sanitary and secondary precipitation drainage systems are advancing according to schedule together with the foundations of the modular buildings. The the Assembly Hall of the Tokamak area, with a slab measuring 5,400m2 and a volume of 1,400 tonnes of steel in total for reinforcement activities, are also documented.
The last cryolines are onsite and their installation will begin soon.