Components

Liquid nitrogen plant getting ready to make ITER cooler

The ITER Cryoplant, the massive refrigerator that will keep magnets and many other systems at low temperature, is getting closer to completion. After the commissioning of the helium storage tanks, which are now filled with this gas, the F4E-ITER Organization Cryogenics Project Team is preparing the distribution line system to operate, in order to supply helium to all the other parts of the cryoplant. At the same time, commissioning of the liquid nitrogen (LN2) plant is ongoing.

A 26 m tall cylinder with a storage capacity of 300 m3 is the protagonist. After being cleaned and purged to remove impurities, the tank was cooled and filled up to 80 % of its capacity, which is the usual working level. For this task, twelve Air Liquide road trailers of 25 m3 each were unloaded into the tank. Nitrogen, like helium, will be used by other systems in the cryoplant and parts of the ITER machine. Liquid nitrogen is taken from the storage and is pressurised by a system of pumps, to be later warmed up to room temperature by heaters, to be subsequently directed to the different systems. Pumps and heaters are the next pieces of equipment to be commissioned.

Filling the storage tank with liquid nitrogen from a 25 m3 road trailer in Cadarache, France, April 2022. © F4E

“The past few months allowed the integrated project team to arrange the work in the best way to use efficiently resources and to minimise risks. In the coming weeks, we will have to operate much more delicate rotating machinery and I am sure the team will be well prepared for this challenge. Thanks to the team’s dedication and effort, we will reach our goals and deliver the LN2 cryoplant and auxiliary systems,” explains Grigory Kouzmenko, F4E Project Manager.

Liquid nitrogen has a number of uses in ITER: it will help cooling down helium in the 80 K loops and liquid helium plant cold boxes, making it ready to use for other systems such as cryopumps and superconducting magnets. Liquid nitrogen will also be used in the gaseous helium purification systems, or in the gaseous nitrogen generator. This piece of equipment, which takes air, liquefies it and separates the nitrogen from it, is just starting its own commissioning. Getting ready the nitrogen and helium facilities enables the commissioning of the remaining equipment. Step by step, we are getting closer to the complete commissioning of the ITER Cryoplant.

press@f4e.europa.eu

Recent Posts

F4E welcomes European Commissioner for Energy and Housing Dan Jørgensen

Fusion will contribute to Europe’s energy security and competitiveness.

6 days ago

F4E launches the 2026 Technology Transfer Demonstrator Call

Two selected projects will get up to 50.000 EUR to apply fusion know-how in the…

6 days ago

Europe’s fourth Vacuum Vessel sector is ready for ITER

F4E accelerates delivery in collaboration with Ansaldo Nucleare, Westinghouse and Walter Tosto.

2 weeks ago

Vice-President of the European Commission Teresa Ribera visits F4E in Barcelona

F4E Director and staff members present progress in fusion projects and industrial benefits.

2 weeks ago

An award for Europe’s heavy transport and logistics for ITER

F4E, Daher and CFT barge operations receive ‘Green Shipper’ prize at an international forum.

3 weeks ago

Europe’s economy benefits from F4E activities according to new study

Close to 6 billion EUR of added value and 5,600 jobs per year generated in…

1 month ago