Construction

Read about the latest progress on the ITER site and watch our new clip

Progress of the work at the Contractors’ area on the ITER site, November 2012

On the ITER platform, work is progressing well on the Assembly Hall of the Tokamak complex area. This 57 metre high building of 5400 m² is located next to the Tokamak pit, and will host the two main cranes of 750 tonnes that will support the assembly of the components of the ITER machine. In November, the pouring of the blinding concrete was concluded and the reinforcement activities that will end up using approximately 1,400 tonnes of steel carried on. The first plot of structural concrete was poured in mid-November and the next plot will be poured in the next days.
Progress has also been made around the Tokamak complex area where excavation works for pipes, water drainage and galleries have started. As far as the contractors’ area is concerned, the foundations of the canteen building are completed and 70 modular buildings are installed.

martial

Recent Posts

Europe’s liquid nitrogen plant shows its cooling power

F4E and Air Liquide complete commissioning of major ITER cryoplant system.

1 week ago

Europe’s first ITER Divertor Cassettes ready

F4E and SIMIC celebrate excellence in manufacturing.

2 weeks ago

F4E and ALSYMEX celebrate the completion of the MITICA beam source

A key ITER heating technology ready for the Neutral Beam Test Facility.

1 month ago

Francesco Sette appointed Chair of F4E Governing Board

F4E Director welcomes Francesco Sette and thanks exiting Chair, Carlos Alejaldre, for his leadership.

2 months ago

Europe and Japan reach full accelerator configuration at LIPAc

A major step to achieve record beam operations and prepare for IFMIF-DONES

2 months ago

F4E welcomes European Commissioner for Energy and Housing Dan Jørgensen

Fusion will contribute to Europe’s energy security and competitiveness.

2 months ago