On the ITER platform, work is progressing well on the Assembly Hall of the Tokamak complex area. This 57 metre high building of 5400 m² is located next to the Tokamak pit, and will host the two main cranes of 750 tonnes that will support the assembly of the components of the ITER machine. In November, the pouring of the blinding concrete was concluded and the reinforcement activities that will end up using approximately 1,400 tonnes of steel carried on. The first plot of structural concrete was poured in mid-November and the next plot will be poured in the next days.
Progress has also been made around the Tokamak complex area where excavation works for pipes, water drainage and galleries have started. As far as the contractors’ area is concerned, the foundations of the canteen building are completed and 70 modular buildings are installed.
F4E and partners will construct three additional facilities and two bridges.
Lead the biggest international fusion project to date.
Companies recognised for an outstanding contribution to Europe’s fusion projects.
The software can visualise complex geometric models in 3D within seconds.
New report explains the industry’s evolution over nearly two decades.
F4E commits to provide the accelerator’s injector and raw steel.