Construction

Read about the latest progress on the ITER site and watch our new clip

Progress of the work at the Contractors’ area on the ITER site, November 2012

On the ITER platform, work is progressing well on the Assembly Hall of the Tokamak complex area. This 57 metre high building of 5400 m² is located next to the Tokamak pit, and will host the two main cranes of 750 tonnes that will support the assembly of the components of the ITER machine. In November, the pouring of the blinding concrete was concluded and the reinforcement activities that will end up using approximately 1,400 tonnes of steel carried on. The first plot of structural concrete was poured in mid-November and the next plot will be poured in the next days.
Progress has also been made around the Tokamak complex area where excavation works for pipes, water drainage and galleries have started. As far as the contractors’ area is concerned, the foundations of the canteen building are completed and 70 modular buildings are installed.

martial

Recent Posts

F4E delivers all equipment to distribute cooling power in ITER

The last cryolines are onsite and their installation will begin soon.

4 days ago

ITER Test Blanket Modules move forward

Europe advances its two concepts through Preliminary Design Review.

1 week ago

Europe develops a new fuel source for JT-60SA

A key technology mastered as F4E and Sener deliver centrifuge accelerator.

3 weeks ago

Europe gets ready to manufacture ITER’s upper launchers

F4E and partners finalise the design of a complex plasma heating component.

3 weeks ago

F4E Supply Chain Excellence Awards launched

Five categories to recognise outstanding industrial contributions in fusion.

4 weeks ago

F4E publishes the first Global Fusion Energy Trends report

What is the state of play in funding, research, patents and devices?

1 month ago