The ITER construction site is undergoing a true transformation with works carried out in the critical network where 150 metres of pipes need to be installed and the overflow area where we are digging 10 metres deep and have to cover an area of 360 metres with more pipes.
Currently, the personnel directly involved in construction counts 200 people and by mid-2014 it is expected to reach 3,000 people. So how are works progressing on that front?
In the contractors area 70 modular buildings have already been installed, which will operate as a canteen, and the first modular offices have been put together ready to host 50 people.
Earthwork activities have progressed according to schedule and more works have been carried out at the Assembly Hall where another load of concrete was poured.
Visit our image library and the F4E YouTube channel to see for yourself the works.
Close to 6 billion EUR of added value and 5,600 jobs per year generated in…
Commissioning will lead to new plasma operations by the end of 2026.
Close to 900 sensor coils around the machine to track the plasma.
The company adapted a robotic metrology tool from ITER to the automotive industry.
Teamwork by F4E and AMW consortium to deliver on schedule.
A major step in commissioning by F4E and Ampegon.