Construction

See the progress of the ITER site

Installing the modular buildings of the canteen which will serve 1500 meals per day, December 2012


The ITER construction site is undergoing a true transformation with works carried out in the critical network where 150 metres of pipes need to be installed and the overflow area where we are digging 10 metres deep and have to cover an area of 360 metres with more pipes.

Currently, the personnel directly involved in construction counts 200 people and by mid-2014 it is expected to reach 3,000 people. So how are works progressing on that front?

In the contractors area 70 modular buildings have already been installed, which will operate as a canteen, and the first modular offices have been put together ready to host 50 people.

Earthwork activities have progressed according to schedule and more works have been carried out at the Assembly Hall where another load of concrete was poured.

Visit our image library and the F4E YouTube channel to see for yourself the works.

martial

Recent Posts

Europe gets ready to manufacture ITER’s upper launchers

F4E and partners finalise the design of a complex plasma heating component.

4 days ago

F4E Supply Chain Excellence Awards launched

Five categories to recognise outstanding industrial contributions in fusion.

7 days ago

F4E publishes the first Global Fusion Energy Trends report

What is the state of play in funding, research, patents and devices?

2 weeks ago

Europe delivers the last components for MITICA

The beam source and calorimeter arrive in the Neutral Beam Test Facility.

3 weeks ago

Europe’s first remote handling tool is in ITER

F4E and Ansaldo Nucleare deliver machine to install heavy port plugs.

3 weeks ago

F4E Highlights 2025 report released

Europe’s achievements in the fusion ecosystem presented in a visual format.

4 weeks ago