See the progress of the ITER site

Installing the modular buildings of the canteen which will serve 1500 meals per day, December 2012


The ITER construction site is undergoing a true transformation with works carried out in the critical network where 150 metres of pipes need to be installed and the overflow area where we are digging 10 metres deep and have to cover an area of 360 metres with more pipes.

Currently, the personnel directly involved in construction counts 200 people and by mid-2014 it is expected to reach 3,000 people. So how are works progressing on that front?

In the contractors area 70 modular buildings have already been installed, which will operate as a canteen, and the first modular offices have been put together ready to host 50 people.

Earthwork activities have progressed according to schedule and more works have been carried out at the Assembly Hall where another load of concrete was poured.

Visit our image library and the F4E YouTube channel to see for yourself the works.

martial

Recent Posts

F4E and ALSYMEX celebrate the completion of the MITICA beam source

A key ITER heating technology ready for the Neutral Beam Test Facility.

4 days ago

Francesco Sette appointed Chair of F4E Governing Board

F4E Director welcomes Francesco Sette and thanks exiting Chair, Carlos Alejaldre, for his leadership.

2 weeks ago

Europe and Japan reach full accelerator configuration at LIPAc

A major step to achieve record beam operations and prepare for IFMIF-DONES

3 weeks ago

F4E welcomes European Commissioner for Energy and Housing Dan Jørgensen

Fusion will contribute to Europe’s energy security and competitiveness.

1 month ago

F4E launches the 2026 Technology Transfer Demonstrator Call

Two selected projects will get up to 50.000 EUR to apply fusion know-how in the…

1 month ago

Europe’s fourth Vacuum Vessel sector is ready for ITER

F4E accelerates delivery in collaboration with Ansaldo Nucleare, Westinghouse and Walter Tosto.

1 month ago