Validating the best welding techniques to deliver ITER Test Blanket Modules

TIG welding robot performing preliminary welding procedures on a full size mock-up of the Test Blanket Modules box.

There are many interests vested in ITER. Broadly speaking, the majority of people count on it to find out how fusion power could contribute to tomorrow’s energy mix. Others, however, are prepared to go one step further, and use the biggest fusion device as a stepping stone, in order to extend their know-how and transfer it to the machine that will follow. Engineers working in the field of Test Blanket Modules (TBMs) belong in the latter category and are seeing beyond the near future. Here is why: to achieve a fusion reaction we need deuterium and tritium— two hydrogen isotopes that in the case of ITER will be supplied. In future, scientists would need to find a way to breed tritium in the machine. The role of TBMs is to explore this possibility to make the fusion power plants of the future self-sufficient.

Europe has developed two types of TBMs that will be located at the 16th equatorial port of ITER. Each of them will consist mainly of steel box containing the tritium breeder, neutron multiplier materials as well as a series of heat extraction plates. During the last two years, technicians had to manufacture mock-ups of these boxes in various sizes, in order to identify the best welding techniques that will be applied at the time of production. F4E together with a large group of partners consisting of Atmostat, CEA Saclay/Grenoble, Alsyom, Commercy, Airbus, Bodycote and CETIM have successfully developed a preliminary welding procedure on a full size mock-up of the TBM box measuring 1.7 x 0.5 x 0.7 m.

Positioning the arm of the TIG welding robot inside the limited space of the full size Test Blanket Modules box mock-up.

The challenging task was carried out using a Tungsten Inert Gas (TIG) welding robot to carry out the welding operations in the tight and limited space of the box. In order to cope with any distortions resulting from the operation, and keep the surface of the box intact without damaging any of its internal channels, special clamping tools were designed and used during tests.

The exploration of welding procedures is expected to come to an end during the next two years in order to draw some technical conclusions. After welding procedures conclude the cycle of qualification, in line with the regulatory requirements, then the real manufacturing phase will begin. In future trials the box will be made of EUROFER97, the candidate steel that Europe is considering to use for TBMs, which responds well to neutron activation with a good resistance to neutron

Samples of EUROFER97 material produced by Saarschmiede GmbH Freiformschmiede on behalf of F4E

The production of EUROFER97, contracted to Saarschmiede GmbH Freiformschmiede, has been completed. A total of approximately 27 T have been manufactured in the form of special plates and bars of various thicknesses from 1.2 to 45 mm.

Representatives of Saarschmiede GmbH Freiformschmiede (L-R) A. Neumann, V. Wagner and N. Lang next to EUROFER97 boxes
martial

Recent Posts

F4E presents Llevant, a breakthrough in nuclear analysis

The software can visualise complex geometric models in 3D within seconds.

3 days ago

How did F4E build the European fusion supply chain?

New report explains the industry’s evolution over nearly two decades.

6 days ago

Europe signs its first Procurement Arrangements for IFMIF-DONES

F4E commits to provide the accelerator’s injector and raw steel.

2 weeks ago

Swiss expertise to power up ITER

F4E and Ampegon hand over more power supplies and will provide two extra units.

2 weeks ago

The first Inner Vertical Target is ready for ITER

F4E and Research Instruments advance in series production.

4 weeks ago

Europe’s final ITER Vacuum Vessel sector delivered

The arrival of ITER’s last extra-large component closes a 16-year manufacturing journey by F4E and…

4 weeks ago