Components

Europe’s liquid nitrogen plant shows its cooling power

Creating a plasma ten times hotter than the Sun requires a powerful supply of cold. This temperature paradox lies at the heart of ITER. In the world’s biggest fusion reactor, a set of magnets will be cooled down with supercritical helium at 4 K (-269 °C) to become superconducting and confine the plasma at 150 million °C. Besides, helium will also be dispatched to the cryopumps to create the vacuum in the reactor, whilst thermal shields will need gaseous helium at 80 K (-193 °C).

Producing such cold fluids takes a massive infrastructure. The ITER cryoplant, located next to the Tokamak Complex, is the size of a football field and features a vast range of equipment. A large part of it bears Europe’s industrial stamp. Fusion for Energy (F4E) has been collaborating since 2013 with the French firm Air Liquide to provide the liquid nitrogen (LN₂) plant plus various auxiliary systems.

After intensive years of installation and tests, the LN₂ plant is now ready for service. The European teams successfully cooled down the two nitrogen refrigerators, completing the commissioning of the system. The plant showed that it can deliver the cooling power required (1,300 kW at 80 K) and can perform reliably in various scenarios. Soon, it will be handed over to ITER Organization, responsible for its operation as a pre-cooler for the helium refrigerators.

The nitrogen’s circuit runs through a set of equipment, including compressors, cold boxes and the 26-meter-tall storage tanks. Commissioning involved a sequence of carefully planned steps. It began with checking mechanical, electrical and control circuits; cleaning the lines and filling them with working fluids.The different components were then operated with nitrogen at room temperature. Once all systems were ready, came the coolest tests: the teams progressively brought down nitrogen to operating temperature and ran a set of performance trials.

Europe’s compressors play a central role in the nitrogen refrigeration cycle. June 2026. ©F4E

Air Liquide experts ran the operations from a control room attached to the cryoplant. Grigory Kouzmenko, Project Manager for F4E, was there to follow it: “Commissioning is an exciting learning process. You see the technologies working in their real environment and, of course, you spot issues along the way. We worked together as a team, with the suppliers and future operators, to ensure reliable operation, apply solutions and rehearse for when ITER is up and running,” he said.

“Achieving the successful commissioning of the nitrogen unit is a pivotal milestone. It highlights the strong collaboration between Air Liquide Engineering & Construction and F4E, reflecting the wider Air Liquide Group’s dedication to ITER. We are honoured to bring our unique cryogenic expertise to this groundbreaking project,” said Frédéric Debert, Commissioning manager at Air Liquide.

Joan Barcelo

Recent Posts

Europe’s first ITER Divertor Cassettes ready

F4E and SIMIC celebrate excellence in manufacturing.

1 week ago

F4E and ALSYMEX celebrate the completion of the MITICA beam source

A key ITER heating technology ready for the Neutral Beam Test Facility.

3 weeks ago

Francesco Sette appointed Chair of F4E Governing Board

F4E Director welcomes Francesco Sette and thanks exiting Chair, Carlos Alejaldre, for his leadership.

1 month ago

Europe and Japan reach full accelerator configuration at LIPAc

A major step to achieve record beam operations and prepare for IFMIF-DONES

1 month ago

F4E welcomes European Commissioner for Energy and Housing Dan Jørgensen

Fusion will contribute to Europe’s energy security and competitiveness.

2 months ago

F4E launches the 2026 Technology Transfer Demonstrator Call

Two selected projects will get up to 50.000 EUR to apply fusion know-how in the…

2 months ago