Components

Successful completion of quench protection circuit procurement for JT-60SA

One of the 13 QPC units after installation in Naka, Japan.


Work on JT-60SAis rapidly moving forward: the final acceptance tests of the quench protection circuit (QPC) for the superconducting coils have been successfully completed.

The quench protection circuit has an important safety function in the JT-60SA machine: superconducting coils are needed to confine the fusion plasma, but if, for whatever reason, the coils stop being superconducting, it is necessary to immediately discharge them to avoid damage from overheating. This protective function is performed in JT-60SA by the 13 QPC units that, when operated, allow rapidly dissipating the huge magnetic energy stored in the coils (>2.3 GJ in total) into a set of discharge resistors. The quench protection system applies an innovative hybrid mechanical-static circuit breaker technology to interrupt dc currents of more than 25 kA withstanding reapplied voltages of about 4.2 kV. Large design margin was taken to improve reliability and to further increase it an explosively actuated circuit breaker is included as back-up protection.

The QPC are procured by the Italian Research Council (CNR) acting through Consorzio RFX in Padua, Italy, in the frame of an “Agreement of Collaboration” with F4E. It is the first time such advanced hybrid circuit breaker technology has been used in industrial application for this high current and voltage ratings, and for this reason a dedicated R&D activity has been performed since 2007 in Padua.

In 2010, the contract for the QPC procurement (including design, manufacturing, testing, transportation, installation, commissioning and final test) was entrusted by Consorzio RFX to the Italian supplier Nidec ASI, which endorsed the innovative solution and lunched an intense qualification process with the manufacturing and testing of two complete prototypes before starting the series production of the 13 QPC units in 2013.

Arrival of QPC units in Naka (September 2014)

The QPC installation in Japan started in December 2014, representing the first occasion of activities directly performed by European personnel at Naka Site for JT-60SA: a special VISA dedicated to Broader Approach Activities has been issued by Japanese government for the European personnel involved in the QPC installation.

After the completion of commissioning activities, the final acceptance tests were successfully performed in June 2015, allowing the closure of the QPC procurement activities on 31 July 2015, according to the original schedule. 

martial

Recent Posts

Europe signs its first Procurement Arrangements for IFMIF-DONES

F4E commits to provide the accelerator’s injector and raw steel.

2 days ago

Swiss expertise to power up ITER

F4E and Ampegon hand over more power supplies and will provide two extra units.

4 days ago

The first Inner Vertical Target is ready for ITER

F4E and Research Instruments advance in series production.

2 weeks ago

Europe’s final ITER Vacuum Vessel sector delivered

The arrival of ITER’s last extra-large component closes a 16-year manufacturing journey by F4E and…

3 weeks ago

F4E launches the 2026 Fusion Technology Transfer Award

10,000 EUR for projects that take fusion solutions to the market.

3 weeks ago

F4E and Amazemet sign a collaboration agreement

A framework for cooperation in additive manufacturing and advanced materials.

3 weeks ago