Manufacturing

Cryopanels completed for the MITICA cryopump

MITICA is the test facility located in Padua (Italy) devoted to the validation of the technology required by the ITER neutral beam system. This part of the machine will help to heat the plasma contained in the vacuum vessel. A key component of MITICA is its cryopump, which will ensure the vacuum conditions needed to perform the experiment.

The cryopump consists of 64 pumping sections assembled in a frame. Each pumping section is made of three cryopanels (the components that perform the vacuum pumping function) and four thermal radiation shields (which keep cryopanels at the right temperature). A total of 231 cryopanels have been successfully coated with charcoal and are now ready to be assembled in the MITICA cryopump.

The manufacturing results from a contract signed between F4E and SDMS, which started in May 2018. The cryopanels, made of aluminium, went through different phases until they reached their final stage. After being free issued by F4E, they were first submitted to grit blasting, a process in which microparticles are shot against the surface of the material to give it a particular roughness. Then, experts applied a ceramic glue to the panels prior to spraying the charcoal granules. Finally, experts baked the panels in an oven and performed adherence tests. The entire process was implemented under strict cleanliness conditions to ensure that the panels are adequate to work in vacuum.

SDMS operator inspecting a panel after the charcoal granules application. SDMS, Saint-Romans, France, April 2019.

But why do cryopanels need charcoal coating? Cryopanels pump out thanks to their very low temperature (4 K). In these conditions, particles stick to their cold surface, providing extreme vacuum as a result. The charcoal applied is a very porous material, thereby multiplying the effective surface area on which gas particles can be trapped. One could say that charcoal coated cryopanels act as “air sponges”.

Obtaining a suitable coating process, however, has not been straightforward. “SDMS has already performed charcoal coatings on cryopanels manually in the past. The challenge in this project was to semi-automate the coating process in order to obtain a homogeneous result on all the profiles. SDMS set up a workshop entirely for this purpose and, after several months of tests, settings, adaptations, and thanks to the rigour and expertise of Clément Astruc, Manufacturing Quality Manager, SDMS has developed a reliable and repetitive process,” explains Amanda Rome, SDMS Project Manager.

“After months of trials by SDMS, and close supervision by the F4E team, we finally developed a charcoal coating process that met ITER Organization’s demanding requirements. This result was achieved thanks to the perseverance of the people involved. The supervision efforts of all parties were enforced during series manufacturing in order to avoid deviations,” explains Aurélien Rousseau, F4E Cryoplant & Fuel Cycle Project Manager who followed this contract.

“The outstanding outcome of this project is the result of the close collaboration between SDMS, F4E, ITER Organization and RFX. Together we have been able to make the most of the knowledge acquired so far in charcoal coating to successfully qualify the process and coat more than 230 panels. It’s worth to point out that this is the first time that such a large number of panels are coated with charcoal,” concludes Luis Mora, F4E Cryoplant & Fuel Cycle Technical Project Officer.

press@f4e.europa.eu

Recent Posts

F4E contract signed to deliver ITER assembly tools

Five suppliers will compete to support divertor, neutral beam and port plug handling systems.

5 days ago

Europe delivers all cold valve boxes for the ITER neutral beam cryopumps

F4E and Research Instruments complete the contract on schedule.

1 week ago

Investment in fusion private sector initiatives reaches 13 billion EUR

F4E Fusion Observatory report analyses competing models in US, China and Europe.

2 weeks ago

Multilateral International DONES Agreement signed

F4E, Spain, Japan, Croatia and Italy will cooperate to build IFMIF-DONES.

2 weeks ago

Europe and Japan install a powerful section in LIPAc

The connection to the accelerator will pave the way for groundbreaking operations.

1 month ago

F4E and SAES Rial Vacuum deliver JT-60SA diamond windows

The components will let microwaves into the machine whilst keeping it sealed.

2 months ago