F4E and Walter Tosto pass a key test for the first cassette body

Members of the teams stand next to the tested cassette body at Walter Tosto. ©Walter Tosto
The production of the divertor cassette bodies for ITER is moving forward at the Walter Tosto factory in Chieti. The Italian firm is producing 54 units under two contracts with Fusion for Energy (F4E). The first of the series recently passed hydraulic pressure tests, a success that shows the teams can master a demanding manufacturing process.
The cassette bodies require a high level of precision. The components will sit inside the ITER reactor, so they come with stringent requirements. Their geometry must meet very tight tolerances, and each weld must be flawless and leak tight. F4E and Walter Tosto worked together to develop and apply special welding techniques, with a team of inspectors following the process closely.
The moment of truth comes during the Factory Acceptance Tests. The first cassette body has entered this final stage, which starts with hydraulic pressure tests. This is a widely used method in industry. By injecting pressurised water, engineers verify the response to pressure and the absence of water leaks in the component.
The first unit stood up well to the tests.“The result is a very positive sign for the project. It confirms the structural integrity of the cassette body and demonstrates that our fabrication processes are mature,” explains Vassilis Stamos, F4E Project Manager.
The road to delivery is now clearer, but there are a few checkpoints ahead. After a baking cycle to dry any remove residual moisture, the first unit will go through the sensitive Hot Helium Leak Tests. In fact, Walter Tosto has invested in the infrastructure to carry out these tests in-house. The sequence will then end with functional tests and thorough dimensional inspections.
“This has been a rewarding journey, marked by significant technical challenges and the exceptional complexity of this component. The successful testing of the first units represents a major milestone, with all key manufacturing processes now validated and a solid foundation for completing all 54 units over the coming years,” comments Uros Gutesa, Project Manager at Walter Tosto.